Follow

Global DNS Server Software upgrade

Customer Identification: All Customers
Start Date: Thursday 31-Jan-2019 02:00 NZDT
End Date: Tuesday 5-Feb-2019 08:00 NZDT
Event Type: Planned Maintenance
Subject: Infrastructure Platform Upgrade
Expected Service Impact: Traffic will be automatically migrated to alternative datacenters around 60 minutes before work commences. There is no service impact expected to customer application traffic.

=============================================================
/ Event Description /

RedShield Infrastructure team will be performing a platform upgrade to the global DNS system between January 31st 0200 Hrs -  February 5th 0800 Hrs NZDT. This is to improve the security and stability of the platform. 

/ Items Associated With This Event /

Global DNS server upgrade.

/ Event Updates /

Jan 31st - Auckland upgrade completed.

Feb 5th - Change completed to all locations.

// END //